Production Line Automation — Siemens S7-1500
Outdated S7-300 controls, frequent downtimes, no data collection. Efficiency dropped to 72%.
Full PLC replacement to S7-1500, WinCC Unified SCADA, PROFINET, Turck TBEN remote I/O, IO-Link.
30% cycle time reduction, 99.2% uptime, 22% energy savings. ROI: 14 months.
LPS Inspection — 4500 m² Industrial Hall
Expired LPS qualification report, incomplete documentation, non-compliant bonding, inadequate earth resistance.
Full LPS inspection per OTSZ §279–281, risk assessment (EN 62305-2), earth resistance measurement, remediation plan.
Passed inspection, 100% compliance. Grounding system renovated.
50 kWp Industrial Solar PV
High electricity costs (~€12K/year), unused flat roof (800 m²).
50 kWp system: 120x 420W panels, SolarEdge inverter + optimizers, monitoring, LPS extension.
45% energy savings, ~€5.5K/year savings, 6-year payback. CO₂ reduction: 28 t/year.
Batch Control — Chemical Mixing Plant
Manual recipe management, frequent dosing errors, lack of traceability.
ISA-88 batch control, S7-1500 + WinCC, automatic recipe management, batch record, audit trail.
Dosing errors reduced by 95%, batch cycle time 25% shorter, full GMP compliance.
Office Building Electrical Reconstruction
30-year old electrical system, overloaded main distribution, missing RCD protection.
Full reconstruction: new distribution, RCD protection, LED lighting with DALI, surge protection.
40% energy savings (lighting), code-compliant protection, 20-year lifetime.
120 kWp Factory Solar PV
€25K/year energy costs, 2000 m² flat roof, high daytime consumption.
120 kWp, 280 bifacial panels, 3x Fronius Tauro inverters, monitoring, LPS extension.
55% self-consumption, ~€14K/year savings, 5.5-year payback.